Construction Related Notice: 01/30/2022: A section of Bishop Boulevard will be closed for storm line installation related to the Cox School of Business construction project

Construction Related Notice
Phase One of the storm line installation related to the Cox School of Business construction project will be complete on January 30.

The Bishop Boulevard closure will move to the Phase Two location identified on map below.

SCHEDULE
Phase One Completion: January 30, 2022
Phase Two Start date: January 31, 2022
Phase Two Completion: Second week in April 

NOTICE
Sidewalks will remain open

Parking will not be impacted

Parking lot J will be accessible via Bishop Boulevard northbound lane

Bishop Boulevard traffic will be two way north of Binkley Avenue cross section

Construction site fence will be enclosed on all four sides, see map for details